Electricity used in Manchester may have been generated in the Trent Valley travelled along cables attached to pylons and travelled under the scenic Peak District before reaching Manchester 's consumers.
Trent Valley
Trent Valley
![]() |
Pylons bring power to Dunford Bridge Station |
Woodhead Tunnels
High-voltage cables were installed in disused Victorian railway tunnels in the 1960s, helping to bringing electricity supplies to Manchester from power stations east of the Pennies in the Trent Valley .
The decision to put cables in the 3 miles 13 yards (4,840 m) Victorian tunnels, rather than building overhead power lines, was made by the Peak Park Planning Board. The two parallel Victorian Woodhead tunnels, between Dunford Bridge Station and Woodhead Station, were bought by the Central Electricity Generating Board (CEGB) and now form part of the 400,000-volt high-voltage grid connecting the substations at Thorpe Marsh, near Doncaster, and Stalybridge, east ofManchester.
The Future
The 1960s cables laid in the two single track Victorian Woodhead Tunnels have a life of about 50 years so in 2011 are now nearing the end of their life and need to be replaced. It is not possible to install new high-voltage cables alongside the existing cables for three main reasons.
The decision to put cables in the 3 miles 13 yards (4,840 m) Victorian tunnels, rather than building overhead power lines, was made by the Peak Park Planning Board. The two parallel Victorian Woodhead tunnels, between Dunford Bridge Station and Woodhead Station, were bought by the Central Electricity Generating Board (CEGB) and now form part of the 400,000-volt high-voltage grid connecting the substations at Thorpe Marsh, near Doncaster, and Stalybridge, east of
The Future
The 1960s cables laid in the two single track Victorian Woodhead Tunnels have a life of about 50 years so in 2011 are now nearing the end of their life and need to be replaced. It is not possible to install new high-voltage cables alongside the existing cables for three main reasons.
- Supply. The supply of power through the Victorian tunnels needs to be unaffected.
- Space. There is not enough room to install new cables in the Victorian tunnels alongside the existing live 400,000-volt high-voltage cables.
- Cost. The Victorian tunnels require considerable works at substantial cost to extend their life.
Work began in February 2008 to install the replacement cables in the third twin track Woodhead Tunnel constructed in 1953. The line and tunnel were closed in 1982, as part of the Beaching line closures, and the tunnel was bought in the 1990s by National Grid as a possible site for the replacement high-voltage cables.
Installing the new high-voltage cable in the third tunnel was expected to take two years to complete, but is still under way in February 2011.
Cables and Wires![]() |
Major engineering work at Woodhead Station to receive the cable from the tunnel. |
Installing the new high-voltage cable in the third tunnel was expected to take two years to complete, but is still under way in February 2011.
